A practical engineering view of NERC Projects 2026-02 and 2026-03, whole-site disturbance behavior, EMT validation and commissioning.
“The next major grid requirement for data centers may not be how much load they add—but how much load suddenly disappears during a disturbance.”
For years, large-load studies have focused primarily on whether the grid can serve a new data center: thermal capacity, voltage performance, short-circuit duty, stability and the network upgrades required to connect the project. That work remains essential. But the reliability question is expanding.
The emerging question is not only whether the grid can deliver hundreds—or thousands—of megawatts. It is whether the complete site can remain predictably connected during a disturbance, how much demand it will shed or transfer, and how quickly active power will return after the fault clears.
That distinction moves the industry beyond model submission. A usable model is the foundation. The next step is demonstrating that the model, the equipment settings and the as-built facility describe the same behavior.
The Grid Problem Is Not Only Load Growth
NERC’s draft Standard Authorization Request for computational-load disturbance performance cites a growing record of customer-initiated load reduction events. In the Dominion Energy Virginia area, NERC describes approximately 1,500 MW of data center load transferring away from the grid during a July 2024 event, about 1,800 MW during a February 2025 event, and roughly 3,800 MW during a July 2026 event.
Those events matter because a large, rapid reduction in demand is itself a system disturbance. It can drive frequency upward, change area-control error, create localized overvoltage, alter interface flows and force operators to reposition resources. The site may not be “lost” in the conventional sense; its customer-side controls may have transferred load to backup supply. From the bulk-system perspective, however, the grid suddenly sees a major demand change.
NERC also notes that sites exposed to similar voltage depressions have not always responded consistently. That uncertainty is the core planning problem: if planners cannot predict how much load will remain, transfer or recover, they cannot reliably simulate the event.
The Requirements Are Moving from Foundation to Performance
Project 2026-02 is the foundational workstream. Its proposed standards address computational-load modeling and data, operational coordination, protection and control information, monitoring and event analysis. The standards passed final ballot in October 2026 and were advancing through NERC’s adoption and regulatory process at the time of publication.
Project 2026-03 is the distinct disturbance-performance workstream. Its scope is aimed at voltage ride-through, frequency ride-through, rate-of-change-of-frequency withstand, post-fault active-power recovery, current consumption during disturbances, performance verification and the point at which compliance should be measured.
This distinction matters. Project 2026-02 helps the grid understand the facility. Project 2026-03 is intended to define how the facility should perform.

Figure 1. NERC’s emerging framework separates foundational model and coordination requirements from site disturbance-performance requirements.
A Data Center Is Not a Single Load
A hyperscale campus is a composite power system. Its response may include utility transformers, medium-voltage switchgear, static transfer switches, UPS systems, battery energy storage, backup generation, variable-frequency drives, chillers, pumps, fans, power-distribution units and thousands of power-electronic IT loads.
Each subsystem has its own controls, protection thresholds, timers and mode transitions. During a voltage depression, some components may ride through, others may reduce current, cooling equipment may stall or trip, UPS systems may move to battery, and backup generation logic may initiate a transfer. When voltage recovers, those subsystems may not return simultaneously.
The system therefore needs a facility-level answer—not only a set of component certificates. The site’s net response is created by the interaction among all of those devices.


Figure 2. Simplified whole-site one-line. The proposed NERC work explicitly raises point-of-measurement, cooling-load and co-located-generation questions.
Ride-Through and Recovery Are Different Requirements
Ride-through asks whether the site remains connected while voltage or frequency stays within a defined envelope. Post-fault active-power recovery asks what happens after the disturbance clears. A site can satisfy the first question yet still create reliability risk if it restores demand too slowly, too quickly, in large discrete blocks or with unstable oscillation.
The Project 2026-03 SAR recommends that the drafting team consider a default recovery level of at least 90% of pre-disturbance consumption, with the recovery level and timing adjustable when system studies justify a different target. It also proposes voltage-duration values as starting points for drafting and recommends addressing repeated voltage depressions caused by automatic reclosing sequences.
Important status note: these values are proposals in a standards-development document. They are not adopted, enforceable NERC requirements. Separate utility, ISO or RTO interconnection requirements may already apply.
| Performance topic | Engineering question | Evidence needed |
| Voltage ride-through | Does the net site remain connected through the specified voltage-time region? | EMT response, relay thresholds, timers and transfer logic |
| Frequency / RoCoF | Do UPS, drives, BESS and protection remain stable during frequency excursions? | Control settings, frequency sweeps and sensitivity tests |
| Post-fault recovery | How much active power returns, how fast, and in what sequence? | Recovery curves, load blocks and restart logic |
| Current consumption | Does fault and recovery current remain within equipment and grid limits? | Waveforms, current limits and transformer behavior |

Figure 3. Illustrative EMT response showing the separate ride-through and recovery questions. The trace is conceptual and is not a compliance test.
Where Performance Is Measured Will Shape the Design
Point of measurement may be one of the most consequential decisions in the standards process. Measuring at an equipment terminal can prove that an individual UPS, drive or battery system has a capability. Measuring at the site point of interconnection captures the combined effect of internal distribution losses, transformer behavior, cooling load, protection, transfer logic and behind-the-meter generation.
The SAR specifically asks the drafting team to consider cooling-load treatment and whether a single net point-of-common-coupling performance region should replace separate load and generation obligations at tightly integrated sites. That question is especially important for campuses with batteries or generation that can mask—or amplify—the grid-facing load response.
Why EMT Modeling and Model Quality Testing Become Essential
Positive-sequence models remain indispensable for bulk-system screening, power-flow analysis and broad stability studies. But many data-center disturbance behaviors occur through fast controls and discrete transitions that positive-sequence models may simplify: UPS current limiting, transfer logic, repeated-fault counters, protection timers, BESS control interaction, motor stalling and staged restart.
An electromagnetic transient model can represent those fast dynamics with greater fidelity. That does not make every EMT model automatically credible. Model quality testing is what turns the file into evidence.
A defensible quality process should confirm:
- The delivered model initializes at the intended operating point and runs without artificial numerical instability.
- Voltage, frequency and phase-jump tests exercise the full disturbance envelope—not only one convenient fault.
- Protection thresholds, timers, current limits and control modes match approved vendor settings.
- The aggregate model preserves the behavior of major subsystems and does not hide critical discontinuities.
- Positive-sequence and EMT models are benchmarked where their valid domains overlap.
- Limitations, black-box dependencies, compiler requirements and version control are documented.
The most valuable deliverable is not a pass/fail screenshot. It is a traceable link from requirement to test case, model response, expected physical behavior and acceptance criterion.
Commissioning Is the Bridge to the As-Built Site
A model can be technically correct when submitted and still become wrong before energization. Vendor substitutions, firmware revisions, revised relay settings, UPS configuration changes, different cooling architecture or modified transfer sequences can all change the disturbance response.
That is why commissioning and as-built validation should be treated as part of the model lifecycle. The process should reconcile final settings against model parameters, verify the actual sequence of operations, capture high-resolution disturbance data where practical and define when the model must be updated after a material change.
The emerging direction is clear: model submission, study acceptance, commissioning and operations will be increasingly connected rather than treated as separate handoffs.
What Developers Should Document Now
1. Define the grid-facing performance objective. Document whether the site is expected to remain connected, transfer internally, reduce demand or recover in stages for each disturbance region.
2. Establish one source of truth for settings. Align equipment schedules, relay files, UPS logic, BESS parameters, generator controls and simulation data under change control.
3. Identify the measurement point early. Resolve whether acceptance is based on equipment behavior, a facility bus or net response at the POI/PCC.
4. Put model data in procurement contracts. Require usable EMT and positive-sequence models, release notes, parameter documentation, technical support and update obligations from vendors.
5. Test recovery—not only ride-through. Evaluate restoration magnitude, timing, ramp shape, block restart, repeated faults and credible operating modes.
6. Design the commissioning evidence plan. Specify metering, event records, test procedures, tolerances, responsibilities and the process for as-built model updates.
7. Keep regional requirements in view. NERC standards development does not replace existing utility, ISO or RTO requirements that may apply earlier or be more stringent.
The Practical Takeaway
The industry is moving toward a whole-site performance obligation. The model will still matter—but the question will no longer stop at whether a file was delivered or whether a study converged.
The stronger question is whether the site can demonstrate predictable disturbance behavior from design through commissioning and operation. For data center developers, that makes ride-through and post-fault recovery an early design decision, a vendor-data requirement, a study requirement and an as-built validation requirement.
Beyond model submission, the new standard of readiness is traceability: requirement → design → model → test → commissioning → operating evidence.
Regulatory Status as of October 26, 2026
Project 2026-02’s proposed foundational standards passed final ballot on October 14, 2026 and were moving to NERC Board adoption and regulatory filing. NERC’s Board separately approved Rules of Procedure revisions establishing Computational Load Owner and Computational Load Operator functional entities; NERC filed those revisions with FERC on October 21, 2026.
Project 2026-03 is an active standards-development effort focused on computational-load disturbance performance. Its SAR and recommended performance values remain proposals. In the United States, a NERC Reliability Standard becomes mandatory only after the applicable approval and implementation steps, including FERC approval.
Primary Sources
- NERC, Project 2026-03 Related Files (updated Oct. 22, 2026)
- NERC, Project 2026-03 Draft SAR (Aug. 26, 2026)
- NERC, Project 2026-02 Final Ballot News (Oct. 15, 2026)
- NERC, Large Loads Action Plan (accessed Oct. 26, 2026)
Learn how RMS Energy supports complex transmission projects here: T&D engineering and consulting services