POI Heat Maps and Detailed Interconnection Studies

What a POI heat map measures

The common screening framework uses a planning power flow model, applies a hypothetical injection at a selected bus, and balances that injection elsewhere in the modeled system. It evaluates the resulting impacts on monitored transmission facilities under selected contingencies.

Figure 1. A hypothetical thermal screen is governed by the more restrictive constraint.

How the regional tools differ

CAISO’s heatmap shows ISO-controlled POIs and available capacity derived from a transfer-limit assessment. Its FAQ makes a critical distinction: the heatmap is different from the deliverability study behind the Constraint Mapping spreadsheet, which is the more appropriate source for available Transmission Plan Deliverability behind known area constraints. The FAQ also states that the heatmap includes P1 contingencies.

A heatmap result therefore cannot be substituted for a project’s deliverability assessment or TPD allocation. Full or Partial Capacity Deliverability Status involves additional requirements and allocation or retention processes. Separately, CAISO publishes POI restrictions and availability information for Cluster 16; electrical screening and practical availability of a connection are separate checks.

The October 2026 guide describes a DC power flow screen consistent with the Capacity Capability Interconnection Standard, while explicitly distinguishing it from a formal CCIS analysis. It uses DFAXs to estimate injection impacts for a selected cluster and scenario. The base map shows the minimum available MW across constraints at each POI; the analysis table uses a 3 percent DFAX criterion relative to the applicable load zone.

The guide says tests at multiple POIs are not cumulative. Interfaces may appear in the table without appearing on the map. Its disclaimer also excludes affected-system impacts and a complete assessment of voltage, fault duty, stability, and EMT behavior. The tool is informative for approximate CNRIS capability, not an official interconnection determination.

Energy service and capacity deliverability use different tests

RegionEnergy or basic interconnection terminologyCapacity or deliverability terminology
PJMEnergy injection capability and maximum facility outputCapacity Interconnection Rights and generator deliverability
MISOEnergy Resource Interconnection Service ERISNetwork Resource Interconnection Service NRIS or qualifying ERIS plus firm transmission
SPPEnergy Resource Interconnection Service ERISNRIS with applicable transmission service and resource adequacy requirements
CAISOEnergy OnlyFull or Partial Capacity Deliverability Status and applicable TPD requirements
ISO New EnglandNetwork Resource Interconnection Service NRISCapacity Network Resource Interconnection Service CNRIS
NYISOEnergy Resource Interconnection Service ERISCapacity Resource Interconnection Service CRIS
ERCOTGeneration interconnection in an energy-only marketNo equivalent centralized capacity interconnection product in this comparison

need to be evaluated for the intended use. Deliverability, resource accreditation, and commercial dispatch priority are separate concepts.

For example, PJM’s formal generator deliverability method considers stressed dispatches, seasonal resource output assumptions, and single or common-mode contingencies. This is substantially more specific than checking a favorable thermal screen at the same bus. Deliverability status also does not promise congestion-free operation or a particular energy price.

Withdrawal studies need their own assumptions

Limitations that can change a siting decision

What a detailed project study should produce

AnalysisQuestion it answersUseful output
POI screenWhich locations merit further investigation under the selected case?Candidate ranking and preliminary limiting facilities
Energy injection studyCan the proposed facility export its requested MW under applicable criteria?Project impacts by scenario and contingency with mitigation options
Withdrawal or charging studyCan the grid supply the specified load or charging demand?Import limits, voltage and thermal constraints, and operating dependencies
Capacity or network deliverability studyCan the requested service be supported under the regional deliverability method?Deliverability constraints and upgrades for the requested service
Chronological operating assessmentWhat happens over representative operating hours?Congestion, curtailment, charging, and load-service exposure

Using heat maps in a development workflow