Positive sequence modeling and EMT testing for IBRs
An inverter-based resource (IBR) model can compile in PSCAD and still give a transmission planner the wrong answer. If the modeled inverter uses a different current priority, protection timer or recovery ramp from the unit that will ship, the study can misstate both the size of a disturbance and how much output the plant recovers. NERC’s review of model quality deficiencies documented mismatches involving as-left settings and model data.
NERC findings on IBR model quality deficiencies
What changed this November
On November 3, WECC posted a draft IBR modeling criterion and draft implementation plan for project WECC-0160. The project aims to align model specifications, quality and performance tests, benchmarking, and screening for electromagnetic transient (EMT) studies across the Western Interconnection. WECC is developing it as a voluntary regional criterion. On November 4, NERC announced its final Order 901 milestone filing with FERC, which includes proposed reliability standards. Project submissions continue to follow the applicable utility requirements.
WECC-0160 project and November 3 postings • WECC final project scope • NERC November 4 filing announcement
Which documents govern the submission
| Utility tariff, agreement and technical documents | Applicable model formats, software versions, intake dates, test cases, tolerances and acceptance evidence. |
| WECC data manuals and model guidance | Regional base-case data, approved positive-sequence models, plant representation and validation methods. |
| NERC reliability standards and guidelines | Applicable compliance obligations and phase-in dates. The EMT guidelines describe recommended model and study practices. |
| IEEE 2800 and IEEE 2800.2 | IBR performance and modeling requirements where adopted. The 2026 recommended practice describes test and conformity methods. Utility tariff, agreement and technical documents Applicable model formats, software versions, intake dates, test cases, tolerances and acceptance evidence. WECC data manuals and model guidance Regional base-case data, approved positive-sequence models, plant representation and validation methods. NERC reliability standards and guidelines Applicable compliance obligations and phase-in dates. The EMT guidelines describe recommended model and study practices. IEEE 2800 and IEEE 2800.2 IBR performance and modeling requirements where adopted. The 2026 recommended practice describes test and conformity methods. |
FERC Order 2023’s pro forma framework calls for validated positive-sequence user-defined and parameterized generic models for non-synchronous requests, plus validated EMT models when the provider performs an EMT interconnection study. NERC lists MOD-026-2 as subject to enforcement with phased implementation and MOD-032-2 as subject to future enforcement.
FERC Order 2023 model provisions • NERC MOD standards status • MOD-026-2 implementation plan • IEEE 2800.2-2026
Utilities Across the Western Interconnection

Figure 1. WECC footprint and office locations for the organizations covered in this article. The regional outline is approximate.
The eight utilities and transmission providers reviewed here operate across the West. CAISO is shown separately as the grid operator discussed in the California section.
California ISO and Participating Transmission Owners
On the CAISO-controlled grid, check both the ISO and the participating transmission owner. Positive-sequence, EMT and project-specific protection or interaction studies can have separate review milestones.
CAISO positive sequence and EMT packages
CAISO’s August 2026 IBR Dynamic Model Review Guideline uses GE PSLF .epc and .dyd files. Section 2 checks that elements and parameters read correctly, initialization is free of errors, warnings are resolved or explained, and the model passes a 20-second no-disturbance run. The guide describes flat output as less than 1 MW and 1 MVAr variation, respectively, or 1%. This is a positive-sequence usability check.
The separately published EMT requirements call for a runnable PSCAD case representing the project through the point of interconnection (POI). Include inverter and plant controls, relevant protection, transformer and collector representation, site settings, and the CAISO IBR EMT checklist. Confirm the accepted compiler and PSCAD configuration for the current submittal. CAISO also lists a separate IBR model validation procedure in its technical forms library.
CAISO August 2026 dynamic review guide • CAISO EMT modeling requirements • CAISO EMT submission checklist guidance • CAISO technical data and validation forms
Pacific Gas and Electric
PG&E’s Transmission Interconnection Handbook, Section G2, calls for a verified plant-level PSCAD model for IBRs of 10 MW or higher and a fundamental-frequency short-circuit model. G2 also specifies Real Time Digital Simulator (RTDS) models for 500 kV interconnections. Plan the RTDS deliverable with the protection team where it applies.
Southern California Edison
SCE and CAISO’s joint MOD-032 process describes validation and handover of generator data to the planning base cases. It explicitly allows SCE to update the master case with validated GE PSLF power-flow data while the EMT model is the only outstanding item. That is a base-case update rule. Confirm the project’s EMT review and interconnection milestones separately.
CAISO and SCE MOD-032 data process
San Diego Gas and Electric
For projects subject to a subsynchronous interaction evaluation under Section 7.2 of SDG&E’s generator handbook, the customer finalizes the inverter and submits the PSCAD study report, runnable models, OEM black boxes and CAISO checklist at least six months before the in-service date. The network study covers screened contingencies under heavy-summer and light-load conditions.
SDG&E Generation Interconnection Handbook • July 2026 CAISO and SDG&E data process
Pacific Northwest and Intermountain Utilities
Bonneville Power Administration
BPA’s January 2026 Interconnection Model Requirements separate power flow, positive-sequence dynamics, full-sequence fault models and EMT. For EMT, Section 7 specifies PSCAD 5.0.2 or later, accurate performance across 5–20 µs, snapshot and multiple-run support, and support for replication in other cases. The package includes the applicable attestation, dependencies, settings documentation, site one-line and model limitations.
BPA’s evidence checklist asks how the EMT controls represent the actual product. Where the model does not use real controller code, BPA calls for a separate hardware comparison report, such as hardware-in-the-loop or other hardware tests. BPA identifies its positive-sequence Model Acceptance Tool report and inputs as optional in Section 5.3. Keep that evidence separate from the EMT attestation and verification material.
BPA STD-N-000001-05 • BPA model acceptance tools
PacifiCorp
Business Practice 84 specifies whole-plant EMT for newly interconnecting IBRs at 60 kV or above where individual unit capacity is at least 10 MVA or aggregate capacity is at least 20 MVA. The practice also preserves engineering discretion to request dynamics or EMT data for certain lower-voltage applications. Its appendix includes separate steady-state, short-circuit, positive-sequence and EMT checklists.
Appendix C gives a concrete positive-sequence test package. It calls for a 5–10 bus equivalent in PSS/E version 34 or higher and a 10-second flat run. Its bump applies a three-phase-to-ground POI fault after one second, with normal clearing tied to voltage level. The appendix calls for the PSS/E user-defined model and library at least six months before commercial operation. Check the earlier cluster agreement or written request milestones for the other data under the practice.
PacifiCorp Business Practice 84
Idaho Power
Idaho Power’s cluster submission checklist includes a validated PSCAD model and a validated positive-sequence user-defined dynamic model for non-synchronous generator submissions, alongside appropriately parameterized generic models. The checklist also asks for evidence supporting the user-defined model and identifies GE PSLF for the generic dynamic models.
Its transmission facility requirements ask for a site-specific sample case to the POI connected to a single-machine infinite bus (SMIB) at a representative short-circuit ratio (SCR). The document calls for accurate operation at a 10 µs timestep or higher, operation across a range of timesteps, and completion of Idaho Power’s EMT Model Test Checklist on OASIS. Use the current OASIS checklist to set the actual pass criteria and cases.
Idaho Power cluster checklist • Idaho Power facility requirements Section 5.4
Arizona Utilities and the Plant Model Package
Arizona Public Service
APS’s published application modeling business practice calls for a consistent GE PSLF power-flow and dynamic package with flat and bump testing. The bump is a normally cleared three-phase POI fault. APS gives clearing times by voltage class and expects stable recovery of active power and appropriate reactive response at the regulated bus. Its published practice states that EMT models are required for new cluster requests beginning with the first regular cluster in 2024, with transitional requests handled as needed.
APS application modeling business practice
Salt River Project
SRP’s grid-forming (GFM) battery business practice applies when SRP specifies GFM operation for a standalone battery energy storage system (BESS) or a co-located BESS component. The published practice excludes hybrid plant BESS components from that specific provision. It calls for a validated EMT model and a performance report after final equipment selection. Its test trips the last synchronous source in a defined testbed and checks whether the battery can transition from charging to discharging and stabilize the island with the specified voltage and frequency response.
SRP GFM BESS business practice • SRP facility connection requirements
Four model representations of one plant

Figure 2. Power flow, positive-sequence dynamics, short circuit and EMT are four representations of the same plant.
Use one plant configuration record across all four representations. Reconcile inverter quantities, MW and MVA bases, transformer taps, collector losses, power plant controller (PPC) sensing point, protection settings and modeled operating modes. Track each value to the design or OEM setting that governs it.
WECC IBR modeling guideline • WECC approved dynamic models • WECC data manuals • NERC EMT guideline
EMT Model Quality Testing in PSCAD

Figure 3. Conceptual SMIB testbench. Implement the required sequence network and grounding for unbalanced faults.
Start with a solved operating point and freeze the software versions, timestep, plant configuration, grid equivalent and event schedule. Repeat at the operating points and grid strengths that apply to the project. For storage, include charging and discharging and consider near-zero dispatch and state-of-charge limits where relevant.
| Build and portability | Compile on a clean install. Verify dependencies, warnings, snapshots, multiple instances and timestep sensitivity as required. |
| Initialization and flat run | Match target MW, MVAr and voltage. Check drift, limiter status, unit availability and consistency between fresh and snapshot starts. |
| Normal controls | Step P, Q or voltage references in the applicable modes. Verify polarity, deadbands, droop, ramp rate, limiter transitions and settling. |
| Fault and recovery | Apply prescribed balanced and unbalanced faults or voltage profiles. Record phase quantities, current priority, trip flags, clearing and recovery. |
| Frequency and phase events | Test prescribed frequency steps or ramps and phase-angle changes. Track headroom, response delays, PLL behavior where applicable, and recovery. |
| Weak grid and GFM | Repeat selected tests across credible grid conditions. For designated GFM resources use the specified performance testbed and mode. |
Use the utility’s fault durations, voltage and frequency profiles, tolerances and required channels. Report both the numerical usability result and the plant performance result for each relevant case.
NERC EMT modeling guideline • NERC EMT system study guideline • Idaho Power facility requirements Section 5.4 • SRP GFM BESS business practice
Benchmarking and a 200 MW Battery Example
Match the inputs before judging the traces
Compare the detailed EMT model with its aggregate EMT equivalent where applicable. Then benchmark the positive-sequence generic and user-defined models against a verified EMT model for responses both domains can represent. Align the POI, P and Q dispatch, pre-event voltage, controller mode, measurement polarity, MVA bases, grid equivalent and disturbance timing. For comparison with RMS models, extract consistent fundamental-frequency or positive-sequence quantities from EMT.
Compare pre-event offsets, peaks, recovery times, steady-state error and the timing of current limits, control transitions or trips. Document the measurement method and error window. A positive-sequence model can match the slower recovery while missing fast switching effects, unbalance or control interactions outside its bandwidth. Record those limitations and use the appropriate domain to assess the behavior.
NERC EMT modeling guideline • WECC IBR modeling and validation guideline

Figure 4. Synthetic active-power traces demonstrate a comparison metric. This example uses analytical curves.
A reproducible weak grid sensitivity
Consider a hypothetical 200 MW battery rated 220 MVA. For this example, define SCR as available grid short-circuit MVA at the POI, excluding the battery’s contribution, divided by the 220 MVA facility base. Assume a 1.0 pu prefault voltage and X/R of 10. The table gives two deliberately selected grid equivalents. Actual utility SCR definitions, study conditions and thresholds may differ.
| Example SCR | Grid short circuit strength | Thevenin impedance on 220 MVA base |
| 5.0 | 1,100 MVA | 0.0199 + j0.1990 pu |
| 2.5 | 550 MVA | 0.0398 + j0.3980 pu |
Interpreting the Weak Grid Sensitivity
Run the same normally cleared three-phase test in both equivalents at the agreed charge and discharge operating points. If the weak-grid EMT case shows delayed active-power recovery, inspect current priority, PPC limits, protection and measured POI voltage first. Repeat at another supported timestep and verify initialization. If the behavior persists, report the sensitivity and carry it into the network study when relevant.
A single SCR value is a screening input. The network study may also need neighboring IBRs, series compensation, a relevant outage topology or other fast controllers. That study tests system interactions. The SMIB case isolates the plant response and makes results easier to reproduce.
NERC EMT system study guideline • NERC EMT modeling guideline
Field Validation and Model Handover
Validate the model against the installed equipment
At procurement, tie the delivered model to the inverter and PPC product variants, firmware, parameter sets, and known limitations. Collect OEM validation evidence, such as laboratory or hardware-in-the-loop comparisons, with the configuration used for the test. At commissioning, compare the installed settings with the study model and use available approved tests or recorded disturbances to validate relevant plant responses. PMU and disturbance recorder data can provide independent evidence where the measurements and event information support the comparison.
WECC IBR modeling and validation guideline • NERC EMT modeling guideline

Figure 5. Track model and test evidence across the project lifecycle.
What to deliver for a reproducible review
Plant definition. Provide the one-line, equipment and controls register, POI definition, MVA bases, transformer and collector assumptions, model versions, control modes, and configuration differences across simulation domains.
Executable files. Include required models, runnable cases, linked binaries and libraries, software and compiler versions, supported timesteps and a run guide. Identify the approved secure route and license or access conditions for OEM files.
Test evidence. Provide a case register, test inputs, comparable plots, native channel outputs where requested, measured response metrics, pass criteria and exception dispositions. Tag each result with the model version that produced it.
Attestations and ownership. Include the applicable equipment and plant attestations and the evidence behind them. Assign ownership for model maintenance and identify which settings and firmware changes require notification or repeat testing.
Control model changes through commercial operation
An inverter swap, a PPC firmware change or a revised ride-through setting can invalidate an earlier comparison. Assess the impact across the model domains, rerun the affected tests, and confirm with the transmission provider whether an update or restudy is required. Preserve both the studied and as-built packages so the reviewer can trace what changed and when.
PacifiCorp Business Practice 84 • SRP GFM BESS business practice • NERC EMT modeling guideline • MOD-026-2 implementation plan
Plan model validation before procurement
Before placing the equipment order, confirm the utility’s submission dates and acceptance criteria. Put four milestones in the interconnection schedule and assign an owner and required evidence to each one. Cover the initial model submission, validated model delivery, network study delivery and as-built handover.
A reviewer should be able to rerun a critical disturbance, explain material differences between the positive-sequence and EMT responses, and trace the settings behind those results to the equipment installed in the field.
When does your team first get a site-specific EMT model it can run and benchmark?