Beyond Positive Sequence Analysis

EMT Model Quality Testing Across ISO and RTO Markets

RMS Energy Industry Insight | Part 3 | September 2026

What model quality testing needs to establish

The Requirements Are Converging—But They Are Not Identical

How the seven markets compare

MarketTesting approachImportant distinction
PJMDefined PSCAD MQT and designated PSS/E benchmarksAs-designed and as-built evidence differ; some implementation dates remain pending in the cited guideline. [1]
MISOStructured tests and overlays across required platformsAppendix I applies to DPP 2025 and later; model packages mature through development and commissioning. [2]
ISO New EnglandDetailed IBR model acceptance testsSeparate performance and benchmarking criteria; not every test requires an overlay. [3]
NYISODefined EMT test suite with applicable phasor comparisonsQualitative consistency and explanations matter; applicability differs for non-IBR facilities. [4]
ERCOTModel quality tests plus separate unit validationTechnology-specific requirements and PSS/E, PSCAD and TSAT comparisons, with stated exceptions. [5]
SPPCurrent EMT requirements and test checklistBroader multi-platform requirements in September 2026 materials are proposals, not current mandates. [6, 7]
CAISOEMT model documentation and response testingRequirements already exist; the cited guideline is not a universal PSS/E overlay matrix. [8]

PJM and MISO

ISO New England and NYISO

ERCOT and SPP

CAISO and the limits of benchmarking

What developers should require from model suppliers

The next question for every EMT submission

Learn how RMS Energy supports complex transmission projects through our T&D engineering and consulting services

Official sources

Open official source

Open official source

Open official source

Open official source

Open official source

Open official source

Open official source

Open official source

Tags

Share